Rohr Road (Bixby Road to Shook Road)

Widening of Rohr Road to 3-lanes from Bixby Road to Shook Road (1.05 mile), including curb and gutter and storm sewer replacement.
PROJECT TYPE:
Highway
COST:
$3,548,334.79
BEGIN CONSTRUCTION DATE:
4/27/2026
FINAL COMPLETION DATE:
4/30/2027
MAINTENANCE OF TRAFFIC:
Phase 2B (60-days): 6/1/26 to 8/14/26
Phase 2A (21-days): 6/1/26 to 8/14/26
Phase 2C (weekend): 6/1/26 to 8/14/26
Phase 3 (21-days)
Phase 4 (60-days)
Phase 5 (60-days)
FUNDING:
DESIGN CONSULTANT:
Kimley-Horn
CONSTRUCTION CONTRACTOR:
Strawser Paving
CONSTRUCTION INSPECTOR:
Shaun Armstrong
CONSTRUCTION YEAR:
2026
LOCATION:
Rohr Road From Bixby Road to Shook Road within the City of Obetz
CONTACT INFORMATION:
Phone: 614-525-3030
Email: fracoeng@franklincountyengineer.org