Rohr Road (Bixby Road to Shook Road)

A progress bar with three stages: IN DESIGN, UNDER CONSTRUCTION (highlighted with a check mark), and COMPLETE (greyed out). The process is currently at the UNDER CONSTRUCTION stage.
Widening of Rohr Road to 3-lanes from Bixby Road to Shook Road (1.05 mile), including curb and gutter and storm sewer replacement.

PROJECT TYPE:

Highway

COST:

$3,548,334.79

BEGIN CONSTRUCTION DATE:

4/27/2026

FINAL COMPLETION DATE:

4/30/2027

MAINTENANCE OF TRAFFIC: 

Phase 2B (60-days): 6/1/26 to 8/14/26

Phase 2A (21-days): 6/1/26 to 8/14/26

Phase 2C (weekend): 6/1/26 to 8/14/26

Phase 3 (21-days)

Phase 4 (60-days)

Phase 5 (60-days)

FUNDING: 

DESIGN CONSULTANT: 

Kimley-Horn

CONSTRUCTION CONTRACTOR: 

Strawser Paving

CONSTRUCTION INSPECTOR: 

Shaun Armstrong

CONSTRUCTION YEAR: 

2026

LOCATION:

Rohr Road From Bixby Road to Shook Road within the City of Obetz

CONTACT INFORMATION: 

Phone: 614-525-3030
Email: fracoeng@franklincountyengineer.org