Beach Road Bridge 0.00 over Big Darby Creek

A progress bar with three stages: IN DESIGN, UNDER CONSTRUCTION (highlighted with a check mark), and COMPLETE (greyed out). The process is currently at the UNDER CONSTRUCTION stage.
Rehabilitate the Beach Road Bridge by investigating for grout voids in ducts, remedial grouting, and various other repairs.

PROJECT TYPE:

Bridge

COST:

$1,929,233.23

BEGIN CONSTRUCTION DATE:

7/7/2025

FINAL COMPLETION DATE:

10/31/2025

MAINTENANCE OF TRAFFIC: 

Full Closure

FUNDING: 

DESIGN CONSULTANT: 

Burgess & Niple

CONSTRUCTION CONTRACTOR: 

VSL

CONSTRUCTION INSPECTOR: 

Burgess & Niple - Mike Kronander

CONSTRUCTION YEAR: 

2025

LOCATION:

Chippewa Street Bridge 0.02 over Barbee Ditch, just west of Amity Road

CONTACT INFORMATION: 

Phone: 614-525-3030
Email: fracoeng@franklincountyengineer.org